Mariott Hotel

About This Project

Customer:

S IMMO AG

Dates:

  • 2 construction phases with 4 months each
  • 170 rooms in construction phase 1
  • 150 rooms in construction phase 2
  • Investment sum: approx. € 20 million
  • 906 m2 Spa & Wellness
  • 16 professional companies in a small space (up to 200 workers)

Services of DELTA:

  • Client counseling
  • Local site supervision
  • Culture management in the construction project

Specifics:

  • Rebuilding during ongoing five-star hotel operation
  • Site logistics, due to strict schedule
  • Regular and strict schedule control
  • Despite the short construction time the quality must be guaranteed
  • A defect-free handover was possible with the tool PlanRadar