Secondary school centre Schärding, Austria

About This Project

Customer:
Bundesimmobiliengesellschaft mbH

Data:

  • Construction period: 19 months
  • Floor area: approx. 3,200 2
  • Total area approx. 13,800 2
  • Construction period: June 2005 – January 2007

Services of DELTA

  • General planning
  • Site supervision (construction)
  • Project monitoring
  • Site supervision (building services)

Specifics

  • Construction within an occupied building
  • Phased gutting of the buildings with structural strengthening and complete renovation of all building works including mechanical, electrical and plumbing services.
  • Thermal upgrade of the building envelope.